The offshore crane HLC 295000 has suffered a major setback when a serious accident occurred during a overload test, resulting in two injured persons having to be taken to hospital for treatment.
A further ten persons were treated by paramedics on site.
“At this point we wish the injured persons all the best and hope for a full and speedy recovery,” said Leopold Berthold, Managing Director of Liebherr-MCCtec Rostock GmbH.
“Considering the extent of the damages, we are above all thankful that it did not cause more personal injuries. Our priorities currently lie in fully supporting the investigating authorities in order to contribute to the quickest possible clarification of the accident,” added Berthold.
At this stage in the investigations, the responsible authorities and experts unanimously agree that a broken crane hook was the cause of the accident.
The exact reasons as to why the hook did not withstand the load are unclear at this stage of investigations. The design and manufacture of the crane hook was purchased from an external supplier. A design or production error of the Liebherr crane can therefore be excluded.
The overload test for the HLC 295000 was planned for a load scenario of 5,500 tonnes. The lift should have been carried out through the hoisting of a barge.
Carrying out an overload test is a typical procedure for the industry, whereby the crane is tested for its maximum lifting capacity. Currently known facts indicate that the incident occurred at a load of around 2,600 tonnes causing a chain reaction which led to the accident.
According to initial estimates, the damage amounts to a high double-digit million figure.