Gigantic Liebherr HLC 295000 collapsed during load testing

Offshore heavy lift wind installation vessel Orion’s new 5,000 tonne Liebherr crane collapsed during load testing on Saturday 2 May.

Two people were hospitalised and 10 were treated on site for minor injuries in the incident. It happened at the port of Rostock on Germany’s Baltic coast where the vessel is moored. Video footage of the incident shows the crane’s main lattice booms flip over backwards and a broken hook hanging from the main hoist lines.

Heavy lift DP3 vessel Orion is 216 metres long, has a beam of 49 metres and a draught of 16.8 metres. The vessel is owned by Cosco (Qidong) Offshore in China. Belgian offshore specialist contractor DEME Group was due to take delivery in the second half of May for operation by its subsidiary GeoSea.

“The crane has suffered significant damage, while damage to the crane and the vessel will be investigated in the upcoming days and weeks,” DEME Group said.

A video of the HLC 295000 can be see below:

Commenting on the incident, Leopold Berthold, Liebherr-MCCtec Rostock managing director, said, “At this point we wish the injured persons all the best and hope for a full and speedy recovery.”

A Liebherr statement read as follows: ”At this stage in the investigations, the responsible authorities and experts unanimously agree that a broken crane hook was the cause of the accident. The exact reasons as to why the hook did not withstand the load are unclear at this stage of investigations. The design and manufacture of the crane hook was purchased from an external supplier. A design or production error of the Liebherr crane can therefore be excluded.”

Liebherr said the failure happened when there was a test load of around 2,600 tonnes on the hook. The full load test would have been 5,500 tonnes, lifting a barge. The company made an initial estimate that the damage “amounts to a high double-digit million figure.”

The Heavy Lift Crane HLC 295000 is the largest Liebherr has ever built. It has a 35 metre outreach and maximum lifting height is more than 175 metres above the deck of the Orion, Liebherr said. The crane and its 145 metre boom was installed on the vessel at the Liebherr port facility in Rostock earlier in 2019. For the installation Liebherr used its new TCC 78000 portal crane installed for such works at the quayside.

Orion’s first job is scheduled to be the installation of turbine and other jacket foundations plus topside installation for the Moray East wind farm off the coast of Scotland. Consent for construction of an offshore wind farm up to 1,116 MW was granted in 2016. Construction of Moray East is underway and there is also Moray West. Moray East is 950 MW, the total wind farm area is 295 square kilometres and it is 22 km off the coast. Tip height of the turbines will be 204 metres.

DEME Group operates in more than 90 countries, has 5,200 employees and a fleet of more than 100 vessels. Its Belgian roots go back more than 140 years. Turnover was €2.62 billion in 2019.

Leave a Comment

Related Topics

Read More

liebherr ehingen groundbreaking 2025

Liebherr Breaks Ground on Massive Expansion at Ehingen-Berg

Liebherr-Werk Ehingen GmbH has broken ground on a new 54-hectare site in Ehingen-Berg, aiming to boost crane production, logistics, and sustainability.
crane accident

Tragedy in Tamil Nadu: Runaway Crane Kills Two in Kanniyakumari

A crane accident near Kanniyakumari railway station has left two dead and several injured. Authorities suspect brake failure as the cause.
jms risi ltm1100 5 3 handover switzerland 3

What Makes JMS RISI’s New Liebherr LTM 1100-5.3 a Game Changer in Swiss Construction?

JMS RISI makes a bold move with the first LTM 1100-5.3 in Switzerland, deepening their partnership with Liebherr. Here's what that means for the future of Swiss construction.
liebherr ltc 1050 3 1e 300dpi

Argentina’s First Electric Crane: A Quiet Revolution by Transportes Crexell

Transportes Crexell becomes the first company in Argentina’s oil and gas sector to operate an electric crane. Discover how this move toward low-emission lifting is reshaping the industry.
charleston terminal crane collision ntsb2025

NTSB: Communication Breakdown Caused $4.5 Million Crane Collision at Charleston Terminal

The NTSB has blamed a communication breakdown for a $4.5 million crane accident at North Charleston Terminal. The incident underscores the importance of air draft awareness and early coordination.
boise airport hangar collapse crane osha settlement

OSHA Withdraws Citation Against Inland Crane in Deadly Boise Hangar Collapse—with Safety Conditions

Inland Crane has reached a settlement with OSHA following the deadly 2024 Boise hangar collapse. While citations are withdrawn, the company must now enforce new safety protocols.
tokyo crane accident transformer fall 2025

Worker Critically Injured After 300kg Transformer Falls During Crane Operation in Tokyo

A utility worker is in critical condition after a 300kg transformer fell from a crane during pole installation in Tokyo. The incident raises questions about rigging safety and lifting procedures.
liebherr ltm1120 4 2 crane bauma2025

Liebherr Introduces Upgraded LTM 1120-4.2 with LICCON3 Controls at bauma 2025

Liebherr reveals the LTM 1120-4.2 at bauma 2025—a smart evolution of its 120t mobile crane featuring Liccon3 controls, touchscreen tech, and operator-focused updates.
Liebherr Unveils 300-Tonne LR 1300.2 SX Unplugged Electric Crawler Crane at bauma 2025

Liebherr to Debut 300-Tonne LR 1300.2 SX Unplugged Electric Crawler Crane at bauma 2025

Liebherr will debut the LR 1300.2 SX Unplugged at bauma 2025—a 300-tonne electric crawler crane with a 392 kWh battery, 196 m system length, and floating mode capability for clean, high-capacity lifting.
SENNEBOGEN Launches 200-Tonne 6203 E Telescopic Crawler Crane at bauma 2025

SENNEBOGEN Launches 200-Tonne 6203 E Telescopic Crawler Crane at bauma 2025

SENNEBOGEN’s 6203 E telescopic crawler crane makes its debut at bauma 2025. With a 200-ton load capacity, 78 m boom, and advanced control system, it's designed for demanding infrastructure and precast applications.
csm pi bauma 2025 duty cycle crane 6220e 2 36f326568f

SENNEBOGEN Expands Duty Cycle Crawler Crane Lineup with 220-Ton Model 6220 E at bauma 2025

SENNEBOGEN expands its HD crawler crane line with the 6220 E—offering 220-ton capacity, modular design, and advanced safety features. Designed for offshore, dredging, and civil engineering, it debuts at bauma 2025 in Munich.
chinas crane manufacturing impact asia

China’s Boom in Crane Manufacturing: What It Means for Asia and Global Competitors

China’s crane manufacturing boom is transforming Asia’s construction industry and challenging global competitors like Japan and Germany. Discover the implications for regional markets and global trade.
pazola expands fleet liebherr ltm 1300 6 3

Pazoła Expands Its Fleet with Liebherr LTM 1300-6.3 Crane

Pazoła strengthens its crane fleet with the Liebherr LTM 1300-6.3, featuring a 90m boom for superior lifting capacity in demanding industries like wind energy and construction.
crane collapse in tree removal hiroshima 2

Crane Collapse During Tree Removal in Hiroshima: What Went Wrong?

A crane accident in Hiroshima’s Hijiyama Park resulted in property damage and power outages. The incident raises questions about safety protocols in crane operations.
702632 around 11 am on december 12, near jianghua community in the

Crane’s Boom Collapse in Chengdu’s Water Tower Demolition: 1 Dead, 2 Detained, Investigation Underway

A fatal crane collapse during a water tower demolition in Chengdu claimed the life of a worker, just days before his 29th birthday. Authorities are investigating safety lapses, with two individuals detained.
fatal crane collapse rama ii road 1

Fatal Crane Collapse on Rama II Road: Six Dead, Eight Injured

A tragic crane collapse on Rama II Road has claimed six lives and injured eight others. Authorities suspect an overloaded girder as the cause. Learn about the incident, victims, and the impact on traffic.
Item added to cart.
0 items - $0.00