Tiong Woon implements Boom Booster

Tiong Woon Implements Boom Booster For Cc8800 2

As one of the world’s largest cranes, there aren’t many jobs out of the reach of a Demag CC 8800-1 lattice boom crawler crane. Singapore-based lifting and transport specialist Tiong Woon had to go beyond the standard configuration for a recent refinery job. To lift a 100 metre, 510-tonne C3 splitter column the 1,600-tonne capacity crawler crane was fitted with a Boom Booster capacity enhancement kit.

The job was a tandem lift together with a 600-tonne capacity Demag CC 2800-1 lattice boom crawler crane, a smaller sibling of the CC 8800-1, for tailing duty.

Local codes of practice meant that a test lift was carried out away from the actual work site. Having passed this test the crane was dismantled, loaded onto trucks and driven to the Merlimau Road work site. It took five days to set up the crane with its seven-part Boom Booster kit. That is one day longer than for the standard crane. The team consisted of six assembly technicians, six signal people, and two supervisors.

Commenting on the job, Michael Ang, Tiong Woon deputy chief executive officer, said, “To speed up the process, one part of the team took care of assembling the base crane, while the other part took care of setting up the Boom Booster.” In addition to an experienced team, the crane is well designed and there was an unusually large amount of available space for assembly, Ang explained.

For the main lift, Tiong Woon chose BSFVL configuration with a 102-metre main boom plus a 12-metre fly jib at an offset of 14 degrees. There was a total of 400 tonnes of superlift counterweight. The CC 2800-1 tailing crane was in SSL configuration with 42 metres of the main boom and 100 tonnes of superlift counterweight.

Upending the 100 metres by a 4.84-metre column was the biggest challenge on this job. First, the CC 2800-1 picked up one end of the column and lifted it 500 mm. At the same time, the CC 8800-1 lifted the other end and the tailing crane tracked forward until the column was hanging vertically and the CC 8800-1 was taking the entire load. The tailing crane was released from the load and the larger unit moved the column into its final position and set it down in position.

Tiong Woon Implements Boom Booster For Cc8800 1

“Tandem lifts are already complex operations in and of themselves, but when you add a heavy load with this type of dimensions, things get even trickier,” Michael Ang explained. It explains the importance of meticulous planning. Completion was a few days ahead of schedule.

“We were at the work site for a total of 69 days with our cranes and 25 people on average. The fact that the weather conditions were ideal and, especially, that the two Demag cranes have such incredible performance characteristics, played a crucial role in enabling us to finish the project earlier than planned – this goes particularly for the CC 8800-1 with the Boom Booster, which was an absolute requirement in order to be able to lift a load with these dimensions and this weight,” Ang said.

Leave a Comment

Related Topics

Read More

xcmg floating wind fish crane lift
XCMG’s 2,000-ton XGC28000 crawler crane just completed a world-first lift—installing a wind turbine on a floating platform that also farms fish. Here’s how it pulled off this high-stakes operation from shore.
hualong soars zo­omlion crawler crane nuclear hoisting
On October 9, at Zhangzhou Unit 3, Zoomlion crawler cranes completed the hoisting of a 132.5‑ton reactor module—the final internal installation—laying the foundation for dome construction. With a prior 2,000‑ton module lift at Jinshanmen, Zoomlion is redefining precision and reliability in nuclear-scale hoisting.
sany sac1200e all terrain crane bauma2025
At bauma 2025, SANY presents the SCC2000A-EV electric crawler crane, SAC1200E all-terrain, SRE450N rough-terrain crane, and the SPL210 power pack—tailored for the DACH region’s emission-free future.
Liebherr Unveils 300-Tonne LR 1300.2 SX Unplugged Electric Crawler Crane at bauma 2025
Liebherr will debut the LR 1300.2 SX Unplugged at bauma 2025—a 300-tonne electric crawler crane with a 392 kWh battery, 196 m system length, and floating mode capability for clean, high-capacity lifting.
csm pi bauma 2025 duty cycle crane 6220e 2 36f326568f
SENNEBOGEN expands its HD crawler crane line with the 6220 E—offering 220-ton capacity, modular design, and advanced safety features. Designed for offshore, dredging, and civil engineering, it debuts at bauma 2025 in Munich.
crane counterweight configurations explained
Delve into the mechanics of crane counterweights, their configurations in various crane types, and real-world applications highlighting their importance in ensuring stability and safety.
why load charts matter
Load charts are often overlooked in crane operations—but they’re the first line of defense against accidents. Here's why every operator, rigger, and planner should treat them as essential.
luffing jib crane types uses
Luffing jib cranes are designed for confined job sites with limited swing radius. Here's when to use them—and how they differ across tower, crawler, and mobile crane applications.
crawler vs rough terrain cranes soft ground engineering
When soil conditions are poor, equipment selection becomes critical. This article compares crawler cranes and rough terrain cranes from an engineering standpoint to determine which performs best on soft ground.
Item added to cart.
0 items - $0.00