Search
Close this search box.

Twelve mobile cranes in operation during the construction of a pipeline in Delft

default
  • A dozen mobile cranes from Boer B.V. laid a one-kilometre-long pipeline with a predefined curvature
  • The pipeline was drilled into the ground for the district heating network
  • Liebherr cranes performed reliably

A dozen strong for the energy transition: twelve mobile cranes with lifting capacities ranging from 90 to 400 tonnes were used to build a pipeline in Delft in the Netherlands. The mobile cranes lifted a pipeline with a total length of one kilometre in order to bring it into the correct position for insertion into the ground. The pipeline is part of the district heating network, which is currently being expanded in order to convert heating systems to sustainable energy sources.

Richard Rijbroek is an environmental manager at Denys and supervised the construction of the pipeline in Delft. The client is Nederlandse Gasunie NV. Rijbroek explains: “Preparations for the “WarmtelinQ” project have been underway for three years. We will use the residual heat from industry in the port of Rotterdam and from waste incineration plants to heat homes and businesses in South Holland.” The pipeline runs from the port of Rotterdam to The Hague via Vlaardingen.

Cranes bend the pipeline into a predefined curve

A drill head was installed on one side of the 1,000 metre long district heating pipeline, as Harm van Dijk, project manager of the Dutch crane operator Boer B.V., explains: “We are drilling a bore here for the heating network. The pipeline is drilled into the ground.” To do this, the pipeline has to be lifted up and placed in a certain curve so that it is drilled into the ground at a defined angle.

lwe 12 krane boer 2 300dpi

According to van Dijk, the length of the retractable arch is 275 metres: “To get the exact curvature, we form the arch with ten cranes. Each of these cranes lifts 18 tonnes. For this reason we need machines with a capacity of 90 – 140 tonnes here. On the other side of the motorway, we used a 300-tonne and a 400-tonne crane because of the large overhang.” The kilometre-long pipeline cannot be completely pre-assembled on the ground, as a motorway and a bridge cross the route. It was therefore stored on containers at a sufficient height as required.

lwe 12 krane boer 3 300dpi

Source: Liebherr Ehingen (Danube) (Germany), 5 March 2024

Share This Story

Related Topics

Item added to cart.
0 items - $0.00